How to account for 'Weather Days' and wind delays in a crane service bid?
Include historical weather data analysis and establish clear contract terms defining acceptable wind limits and compensation for weather-related standby time.
Weather delays represent a significant cost risk in crane operations that must be carefully quantified during bidding. Analyze historical weather data for the project location and timeframe, focusing on wind speeds above your crane's operational limits and precipitation that could halt work. Most mobile cranes cannot operate safely in winds exceeding 20-25 mph, while tower cranes may have higher thresholds.
Remember: WIND - Weather data, Identify limits, Negotiate standby, Define contract terms